Swift Waterline Replacement 

To all residents on W. 7th St. from Leuty to Jackson St.

The City of Justin and Atkins Construction will be upgrading your water system with the installation of a new 8” water main and water services.

The work will be from 7am-5:30pm Monday through Friday with occasional Saturday work. There may be some temporary drives and lane closures during work hours. All driveways will be open at the end of every workday.

The planned start date for this project is October 4th, 2021. The planned completion date for this project is spring of 2022. Your cooperation will be appreciated. 

If you have any questions, please call:
 Atkins Construction office – (972) 775-7955

Atkins Construction 24-hour contact is Rick Hooper – (214) 794-8084
 (For emergencies only.)

City of Justin Police Department – (940) 648-2541

Click here to view the full schedule.

Click here to view the water layout.

Review the January 15, 2021 - CMP Press Release (DOC).